The Tarp Is Part of the Building While the Wall Is Open
There is a period during every envelope restoration when the building has no envelope.
The cladding is off, the membrane is stripped, the sealant is cut out, and what stands between the interior and a Metro Vancouver autumn is a temporary system that somebody installed that afternoon.
That system is doing the job of the building. It deserves the same attention as the permanent work, and on a lot of projects it gets a fraction of it.
Vertical rain is not the test
Temporary protection that works on a calm day is easy. Sheeting draped over an opening sheds rain falling straight down without difficulty.
That is not the condition this region delivers. Wind-driven rain arrives at an angle, it comes in gusts, and it finds every edge, lap, and unsecured corner in a covering. The mechanism is described in the guide on wind-driven rain, and it is the reason a permanent envelope needs drainage and detailing rather than a single sealed surface.
A temporary system faces the same conditions with none of the redundancy. It has to be secured at every edge, lapped in the right direction, and fixed well enough that a gust cannot lift it.
The second requirement is that it resists uplift on itself. A large sheet that comes loose in a southeasterly is a hazard to the building, to the site, and to the street below, and on a downtown project that is a public safety matter rather than a site inconvenience.
Enclosures are engineered, not chosen
Where a project uses scaffolding with shrink wrap or netting, the covering creates wind loading on the scaffold structure.
That loading is substantial and it has to be accounted for in the scaffold design. A scaffold engineered for an open frame and then wrapped is a different structure carrying a different load, and the wrap is what makes it so.
This is a design item with an engineer’s involvement, not a decision made on site about what to cover the scaffold with. On a project using swing stages or rope access rather than scaffolding, the protection has to be attached to the building instead, which brings its own set of penetrations and reinstatement obligations.
Who owns the water
This needs to be in the contract, and on many strata projects it is not.
Temporary works are generally the contractor’s responsibility, including protection of the open area and any damage resulting from its failure. That is the normal allocation and most contractors accept it without argument.
The problem arises when it is unstated. A resident has water in their suite, the contractor points to an unusually severe storm, the strata points to inadequate protection, and the argument happens after the damage with a distressed owner waiting for someone to accept responsibility.
Settling it in advance costs nothing. Leaving it open costs whatever the dispute costs, plus the goodwill of the affected residents, which on a project with two years still to run is not a minor item.
Insurance is the companion question. Whose policy responds to water damage during construction, what the deductible is, and who pays it, are all questions with clear answers available before the work starts and no clear answers available afterward.
Stopping before the weather arrives
Securing an open area properly takes time. That time has to be available before the weather arrives, not while it is arriving.
Which means the decision to stop work and secure gets made on a forecast, hours ahead, by someone with the authority to make it. On a project without that arrangement, the decision gets made when the rain starts, by a crew already packing up, and the securing is exactly as thorough as the remaining daylight allows.
The contract should name who makes that call and what the securing procedure involves. The monitoring practice set out in the guide on monitoring between storms applies to active construction as much as to a completed building.
Atmospheric river events in this region are forecast with reasonable lead time, and a project running through October and November should treat those forecasts as a scheduled part of the work rather than as interruptions.
Winter work and enclosures
Restoration does not stop for the wet season in Metro Vancouver, and pretending it will produces schedules that ignore half the year.
Full enclosures with heat allow concrete repair, sealant work, and coating application to proceed in conditions that would otherwise prevent them, which is the approach set out in the post on winter restoration and cold-weather coating application.
The trade-off is cost, and it is a real one. It should be weighed against the cost of extending the project into a second season, which brings its own remobilization, extended consultant involvement, and another year of residents living with the work. Neither option is free and the comparison is worth making explicitly.
Pricing it honestly
Temporary protection is a line item and it belongs in the tender documents as a defined requirement rather than as an assumption each bidder makes privately.
Where it is not specified, bidders price it differently. The bid that assumed minimal protection is lower, it wins, and the difference surfaces in November as either inadequate protection or a change order.
Requiring bidders to describe and price their weather protection approach makes the bids comparable and gives the consultant something concrete to review. It belongs in the scope described in the post on envelope tender scope of work.
The daily routine on an open building
Most of the protection failures on restoration projects are not design failures. They are end-of-day failures.
A crew working an elevation opens an area during the day and closes it before leaving. That closing routine is the whole system on most projects, repeated daily for months, and its quality depends on how much time was allowed for it and whether anyone checks.
The practices that work are unremarkable. Stop opening new area early enough in the day that everything opened can be closed properly. Secure at every edge rather than at the corners. Lap in the direction water will run. And have someone other than the person who did it confirm the area is closed before the site is left.
The consultant’s site review should include the condition of temporary protection, because unlike most site observations it has an immediate consequence for the building rather than a long-term one. A poorly closed elevation on a Thursday afternoon is a wet suite on Friday morning.
Fire, security, and the other risks
Weather is the obvious risk on an open building and it is not the only one.
An enclosure or a sheeted scaffold changes the fire situation, both by adding combustible material and by affecting how a fire would spread on the facade. Material selection matters, and flame-spread requirements apply to sheeting and shrink wrap used on occupied buildings.
Scaffolding and access equipment also create a route into the building at levels that were previously unreachable, which is a security consideration for residents and a legitimate source of anxiety. Ladder access removal at the end of each day, alarms on accessible openings, and clear communication about what is being done are standard responses.
Both belong in the project planning rather than being raised by residents partway through, and both are usually straightforward once someone has thought about them. The communication approach in the post on resident communication during envelope restoration covers how to raise them without alarming people.
Protecting the people who live there
Separate from weather, and a reliable source of complaints: residents’ balconies, patios, windows, and belongings need protection from dust, overspray, and debris.
That is a specification item with a straightforward answer, and it goes wrong when it is left to be sorted out on site. What gets covered, by whom, when it goes on and comes off, and who is responsible for anything damaged, are all better decided in writing than after somebody’s patio furniture has been overspray-coated.
The tarp over the open wall protects the building. The sheeting over the balcony protects the relationship with the people paying for the project, and both are worth doing properly.
Sources and further reading
- WorkSafeBC, Occupational Health and Safety Regulation Part 13 and Part 20, temporary structures and construction requirements, referenced 2026
- Canadian Standards Association, CSA S269.2 Access Scaffolding for Construction Purposes, referenced 2026
- BC Housing, Building Enclosure Design Guide, construction sequencing and temporary protection, referenced 2026
- Allweathercoating project records, Metro Vancouver, 2026